SCOPE: To increase flood-carrying capacity and provide erosion protection along the Lower Ivory Channel south of Southern Boulevard.
PROJECT STATUS: Construction
PROJECT DOCUMENTS: Construction Plans
MEETINGS: Pre-Con Meeting (10/26/2022), Weekly Meetings will be held at SSCAFCA (on Wednesday’s)
PROJECT INFORMATION:
CITY: Rio Rancho
WATERSHED: Black
CONSULTANT: SSCAFCA In-House
CONTRACTOR: Salls Brothers
CONSTRUCTION COST: $1,402,083.43 + NMGRT
ADVERTISE: September 2022
CONSTRUCTION START: NTP was 11-7-2022
CONSTRUCTION END: Complete
PRE-CONSTRUCTION PHOTOS:
![](https://www.sscafca.org/wp-content/uploads/2022/11/BOP-225x300.jpg)
![](https://www.sscafca.org/wp-content/uploads/2022/11/Ivory-5-225x300.jpg)
![](https://www.sscafca.org/wp-content/uploads/2022/11/Ivory-2-225x300.jpg)
![](https://www.sscafca.org/wp-content/uploads/2022/11/IMG_1981-300x225.jpg)
![](https://www.sscafca.org/wp-content/uploads/2022/11/IMG_1977-300x225.jpg)
DRONE FOOTAGE:
![](https://www.sscafca.org/wp-content/uploads/2022/11/DJI_0463-300x200.jpg)
POST CONSTRUCTION PHOTOS:
![](https://www.sscafca.org/wp-content/uploads/2022/11/IMG_0068-225x300.jpg)
![](https://www.sscafca.org/wp-content/uploads/2022/11/IMG_0066-225x300.jpg)
![](https://www.sscafca.org/wp-content/uploads/2022/11/20230403_124220-225x300.jpg)
RIBBON CUTTING PHOTOS:
![](https://www.sscafca.org/wp-content/uploads/2022/11/Image-225x300.jpeg)
![](https://www.sscafca.org/wp-content/uploads/2022/11/Image3-300x225.jpeg)
![](https://www.sscafca.org/wp-content/uploads/2022/11/Image2-300x225.jpeg)
![](https://www.sscafca.org/wp-content/uploads/2022/11/Image4-300x225.jpeg)